Construction Updates

1st September 2021 Report

A- Block : Ground floor to First floor shuttering in progress.
B- Block : Second floor to Third floor wall shuttering in progress.
C- Block : Second Floor to Third Floor wall shuttering in progress.
D- Block : First floor to Second floor wall shuttering in progress.
Non Tower Area (East A&B -Block) : Podium slab concrete work in progress.
Non Tower Area (East A&B -Block) : Podium slab concrete work in progress.
Clubhouse : 1st Basement to Ground floor level column and Tanks Shuttering and Concrete work in progress.

1st September 2021 Report

1st August 2021 Report

A- Block: Ground floor to First floor shuttering in progress.
B- Block: Second floor slab shuttering & Reinforcement in progress.
C- Block: 2nd Floor to 3rd Floor wall Reinforcement & shuttering in progress.
D- Block: Ground floor to First floor wall shuttering & Reinforcement in progress.
Non Tower Area (East A&B-Block): Podium slab level shuttering in progress.
Non Tower Area (West C&D-Block): South west podium slab completed, North west Podium slab shuttering in progress.
Clubhouse: 1st Basement to Ground floor level column Reinforcement & Shuttering in progress.

1st August 2021 Report

1st July 2021 Report

A-Block : Ground floor to First floor Reinforcement in progress.
B-Block : First floor to Second floor Reinforcement & shuttering in progress.
C-Block : Second floor level shuttering in progress.
D-Block : Ground floor to First floor Reinforcement in progress.
Non Tower Area (East A&B -Block) : South east Podium slab shuttering in progress, North east retaining wall in progress.
Non Tower Area (West C&D -Block) : South west podium slab completed, North west Retaining wall in progress.
Club house : B2 Level to B1 Columns & Retaining wall Reinforcement & shuttering in progress.

1st July 2021 Report

1st June 2021 Report

A- Block: Ground floor to First floor Reinforcement in progress.
B- Block: Ground floor to First floor Reinforcement completed, shuttering in progress.
C- Block: First floor to Second floor Reinforcement in progress.
D- Block: Ground floor Reinforcement & Shuttering in progress.
Non Tower Area (East A&B -Block): 1st Basement to Podium slab Reinforcement in progress.
Non Tower Area (West C&D -Block): 1st Basement to Podium slab Reinforcement in progress.
Club house: 2nd Basement shuttering in progress.

1st June 2021 Report

1st May 2021 Report

A- Block : Ground floor to First floor Reinforcement in progress.
B- Block : Ground floor to First floor Reinforcement in progress.
C- Block : First floor level slab shuttering in progress.
D- Block : Ground floor shuttering & Reinforcement in progress.

1st May 2021 Report

1st April 2021 Report

A- Block : Ground floor slab Reinforcement in progress.
B- Block : Ground floor slab Reinforcement in progress.
C- Block : Ground floor to First floor walls Reinforcement and shuttering in progress.
D- Block : 1st Basement to Ground floor column and shuttering walls concrete in progress.

1st April 2021 Report

1st March 2021 Report

A-Block : Ground Floor slab shuttering in progress.
B-Block : Ground Floor slab shuttering in progress.
C-Block : Ground Floor transfer slab Reinforcement in progress.
D-Block : 2nd Basement level to 1st Basement level column casting in progress.

1st March 2021 Report

1st February 2021 Report

A-Block : 1st basement slab Reinforcement in progress.
B-Block : 1st basement shuttering in progress.
C- Block : Podium shuttering in progress.
D- Block : 2nd basement Reinforcement in progress.

* Work in progress with adequate work force even in pandemic situation.

1st February 2021 Report

1st January 2021 Report

A-Block : Basement 2 slab work in progress.
B-Block : Basement 2 slab work in progress.
C-Block : Basement 1 columns shuttering work in progress.
D-Block : Basement 3 columns shuttering work in progress.

* Work in progress with adequate work force even in pandemic situation.

1st January 2021 Report

1st December 2020 Report

A-Block: Basement -2 Slab work in progress.
B-Block: Basement -2 Slab work in progress.
C- Block: Basement-1 Shuttering Work in Progress.
D-Block: Raft Concrete work in progress.

* Work in progress with adequate work force even in pandemic situation.

1st December 2020 Report

1st November 2020 Report

A-Block: Basement -2 slab & beam shuttering work in progress.
B-Block: Basement -2 Floor slab & beam shuttering work in progress.
C- Block: Basement-2 Floor slab completed. And basement-2 to basement-1 wall reinforcement work in progress.
D-Block: Raft reinforcement in progress.

* Work in progress with adequate work force even in pandemic situation.

1st November 2020 Report

1st October 2020 Report

A- Block Raft concreting is in progress
B- Block Raft Concrete completed, walls reinforcement in
C- Block basement 2nd floor slab shutteering in progress
D- Block Raft Reinforcement work in Progress

* Work in progress with adequate work force even in pandemic situation.

1st October 2020 Report

1st September 2020 Report

A- Block Raft Reinforcement in Progress
B- Block Raft Reinforcement in Progress
C- Block Basement 3 & 2 Level Column concrete in Progress
D- Block Raft PCC completed

* Work in progress with adequate work force even in pandemic situation.

1st September 2020 Report

1st August 2020 Report

A and B block Tower foundation reinforcement progress
C Block Raft foundation completed and C block Tower basement column reinforcement progress.

* Work in progress with adequate work force even in pandemic situation.

1st August 2020 Report

19th June 2020 Report

19th June 2020 Report

18th May 2020 Report

Sentring Work Completed for 3 Basements.

18th May 2020 Report

18th February 2020 Report

Excavation For 3 Basements Completed.

18th February 2020 Report